This PMI-SP pack was the main thing I studied from, and it paid off on exam day. The PDF worked well on my phone, so...
Every question comes with the verified correct answer and detailed rationale.
Thomas works as a contract-based project manager for BlueWell Inc. Management has hired Thomas to manage a high-risk project because Thomas has years of experience with this technology and similar project. Thomas would like to use his own templates for the project schedule, quality, and risk management approach. Management is fine with this, except after reviewing the template they had preferred Thomas to use 24-hour time periods for his project calendar rather than the 8-hour time periods as indicated. Thomas agrees, but now he has to update what document in his project management plan?
Correct answer: 1
The project calendar needs to be updated to reflect the 24-hour time period rather than the 8-hour
time period.
The project calendar is used to define the working and nonworking days and times for tasks. This
calendar is usually used to represent an
organization's traditional working hours. Project uses this calendar to schedule tasks that do not
have resources assigned or that have a task
type of fixed duration. By default, the Standard base calendar is used as the project calendar. A user
can also reflect alternative schedules by
using other base calendars.
The working days and hours in the project calendar reflect the working days and hours for the whole
project. A user can also specify special
days off, such as company holidays. A user can also indicate other nonworking times to reflect
periods when the whole team will be working
on nonproject activities, such as company meetings or department retreats.
Answer option D is incorrect. The schedule management plan will reference to the project calendar
and the resource calendar. It does not
need to be updated directly as a result of the time period change.
Answer option C is incorrect. The resource calendar does not need to be updated as this document
defines when resources are available.
Answer option B is incorrect. The activities of the project are not changing, only the time periods of
the project calendar.
Virginia is the project manager for her company. She has used a previous project as a basis for her current project because they are similar in nature. Virginia has adapted nearly all of the previous project plans for her current project - including the project schedule, risk register, and communications management plan. She has worked with management to update the plans to adapt them to the current project. What are the previous project management plans called in this instance?
Correct answer: 3
The best answer for this question is a template. When projects adapt previous project
plans for the current project, it is an example of a
project template. Template is an activity list or a part of the activity list taken from the previous
project and used in a new project.
Answer option D is incorrect. A parametric estimate is an estimate that uses a parameter to predict
the costs of the project, such as cost per
network drop or cost per software license. Parametric estimating technique utilizes the statistical
relationship that exists between a series of
historical data and a particular delineated list of other variables.
Answer option A is incorrect. Expert judgment is not the best choice for this question. Expert
judgment is a technique based on a set of
criteria that has been acquired in a specific knowledge area or product area. It is obtained when the
project manager or project team requires
specialized knowledge that they do not possess. Expert judgment involves people most familiar with
the work of creating estimates.
Preferably, the project team member who will be doing the task should complete the estimates.
Expert judgment is applied when performing
administrative closure activities, and experts should ensure the project or phase closure is
performed to the appropriate standards.
Answer option B is incorrect. Analogous is an estimating technique that uses the values of
parameter, such as scope, cost, budget, and
duration or measures of scale such as size, weight, and complexity from a previous, similar activity as
the basis for estimation of the same
parameter for a future activity. It is a top-down estimating technique and is a form of expert
judgment. It provides a lower degree of accuracy
than other estimating techniques. This technique is primarily used when there is a limited amount of
detailed information about the project or
program.
In which of the following process groups does Integration Change Control Process fall?
Correct answer: 4
The Integration Change Control process is a part of Project Integration Management
knowledge area group. It falls under the Monitoring and
Controlling process group. Monitoring and controlling is a process group or stage that starts when
the project is in the executing stage. This
process overlaps the executing stage. Monitoring and controlling consists of those processes
performed to observe project execution so that
potential problems can be identified in a timely manner and corrective action can be taken, when
necessary, to control the execution of the
project. The key benefit is that project performance is observed and measured regularly to identify
variances from the project management
plan. Monitoring and controlling includes:
Measuring the ongoing project activities (where we are).
Monitoring the project variables (cost, effort, ...) against the project management plan and the
project performance baseline (where we
should be).
Identify corrective actions to properly address issues and risks (How can we get on track again).
Influencing the factors that could circumvent integrated change control so only approved changes
are implemented.
In multi-phase projects, the monitoring and controlling process also provides feedback between
project phases, in order to implement
corrective or preventive actions to bring the project into compliance with the project management
plan.
What is Project Integration Management?
Project Integration Management is one of the nine Project Management Knowledge areas. It
comprises the following
processes:
Develop Project Charter
Develop Preliminary Project Scope Statement
Develop Project Management Plan
Direct and Manage Project Execution
Monitor and Control Project Work
Integrated Change Control
Close Project
These processes occur throughout the project and are repeated quite often during the working of
the project. They ensure
that the various elements of the project are properly coordinated.
This PMI-SP pack was the main thing I studied from, and it paid off on exam day. The PDF worked well on my phone, so I could revise on the train and during lunch breaks. I went through the whole pack twice before booking the exam. If you are sitting PMI-SP soon, this is worth having.
I needed something focused for PMI-SP, and this was exactly that. Some of the topics were new to me, but the explanations walked through them in plain language. I kept a notebook of the points I kept getting wrong and revised those again. For the price of a few coffees, it was good value for what it delivered.
I have been working full time while preparing for PMI-SP, so I needed material I could dip into in short sessions. The practice tests helped me get used to the timing, which was my biggest worry going in. I booked the exam once I was scoring well on the practice tests. I would happily recommend it to a friend taking the same exam.
After failing once before, I came back with this PMI-SP pack and passed comfortably. I liked that the questions felt close to the real exam in style, so nothing on the day felt completely new. I studied for about three weeks before the exam. For the price of a few coffees, it was good value for what it delivered.
I needed something focused for PMI-SP, and this was exactly that. The explanations are clear and they helped me understand why an answer was right instead of just memorising it. I spent a couple of weekends working through the practice tests. For the price of a few coffees, it was good value for what it delivered.
A colleague recommended this PMI-SP pack to me, and I am glad I listened. The questions made me think properly instead of just recalling facts, which is what the real exam does too. I revised every evening after work for a month. A few explanations could be a little longer, but overall the pack is solid and it helped me pass.
Honestly I was not sure what to expect from the PMI-SP exam, but this pack made the preparation much clearer. I used the practice questions alongside my notes, and together they covered the exam well. I studied in short bursts most mornings before work. I wish I had found it sooner, it would have saved me a lot of time.
I bought this PMI-SP material a few weeks before my exam and studied it almost every day. I appreciated that the answers were explained properly, because that is how I actually learned the material. I used the last week just to redo the questions I had got wrong. I would happily recommend it to a friend taking the same exam.
I used this PMI-SP material for my final revision and it really helped me feel ready. I used the practice questions alongside my notes, and together they covered the exam well. I started early and took my time instead of cramming at the end. I would recommend it to anyone preparing for PMI-SP.
I needed something focused for PMI-SP, and this was exactly that. I appreciated that the answers were explained properly, because that is how I actually learned the material. I focused on my weak areas in the final few days. If you are sitting PMI-SP soon, this is worth having.
I have been working full time while preparing for PMI-SP, so I needed material I could dip into in short sessions. I appreciated that the answers were explained properly, because that is how I actually learned the material. I went through the whole pack twice before booking the exam. I would happily recommend it to a friend taking the same exam.
The PMI-SP exam covers a lot of ground, so I was glad to have a structured set of questions to work through. The practice tests helped me get used to the timing, which was my biggest worry going in. I read the explanations carefully rather than rushing through the questions. I passed, and I think this material deserves a lot of the credit.
I needed something focused for PMI-SP, and this was exactly that. The explanations are clear and they helped me understand why an answer was right instead of just memorising it. I booked the exam once I was scoring well on the practice tests. I would happily recommend it to a friend taking the same exam.
I needed something focused for PMI-SP, and this was exactly that. I used the practice questions alongside my notes, and together they covered the exam well. I did a little bit each day for a few weeks, which suited me better than long sessions. I would happily recommend it to a friend taking the same exam.
I bought this PMI-SP material a few weeks before my exam and studied it almost every day. I appreciated that the answers were explained properly, because that is how I actually learned the material. I revised every evening after work for a month. There were one or two questions I found confusing, but the rest was spot on and I passed.
I bought this PMI-SP material a few weeks before my exam and studied it almost every day. The practice tests helped me get used to the timing, which was my biggest worry going in. I focused on my weak areas in the final few days. It did the job for me, and I would use the same kind of material again.
I needed something focused for PMI-SP, and this was exactly that. I used the practice questions alongside my notes, and together they covered the exam well. I spent a couple of weekends working through the practice tests. I would happily recommend it to a friend taking the same exam.
A colleague recommended this PMI-SP pack to me, and I am glad I listened. I appreciated that the answers were explained properly, because that is how I actually learned the material. I studied in short bursts most mornings before work. I would recommend it to anyone preparing for PMI-SP.
Not sure yet? Take the free PMI PMI-SP Scheduling Professional practice test first.
This exam is hard because it mixes several topics at once, so you need to keep the whole syllabus in your head on exam day. You have 210 minutes for the whole exam, so time pressure is real. Work through timed practice questions and review each answer, right or wrong, until the reasoning behind every one of them is clear to you.
Every pack comes as 2 PDFs: one with every answer explained, and a questions-only copy for timed practice. Products are delivered instantly as digital downloads, and every pack includes free updates for life.
Question sets are updated regularly. The date of the latest update is shown on every exam page.
Yes. Every pack includes free updates for life.
We correct mistakes as we find them, and the fix ships in the next update, free. If something still looks off, check it against the vendor\u2019s own documentation and contact us.
Most candidates use them as their main practice source. If you study with them and still fail, we refund you in full.
You get your money back. Full terms are in our refund policy.
Credit card, processed securely through Stripe. All prices are shown in USD at checkout.
No. All products are digital downloads. There is no physical shipping.
Please contact us with your order number and payment confirmation details.