What course of action can be taken by a party if the current negotiations fail and an agreement cannot be reached?
A . ZOPA
B . PON
C . Bias
D . BATNA
Correct answer: D
In negotiation theory, the best alternative to a negotiated agreement or BATNA is the course of action that will be taken by a party if the current negotiations fail and an agreement cannot be reached. BATNA is the key focus and the driving force behind a successful negotiator.
BATNA should not be confused with the reservation point or walk away point. A party should
generally not accept a worse resolution than its BATN
Tomas is the project manager of the QWS Project and is worried that the project stakeholders will want to change the project scope frequently. His fear is based on the many open issues in the project and how the resolution of the issues may lead to additional project changes. On what document are Tomas and the stakeholders working in this scenario?
A . Communications management plan
B . Change management plan
C . Issue log
D . Risk management plan
Correct answer: B
The change management plan defines how the change control system works and the proper channels and procedures manages changes within the project. Change control system, a part of the configuration management system, is a collection of formal documented procedures that
define how project deliverables and documentation will be controlled, changed, and approved.
Answer option C is incorrect. The issue log is a document that records all issues, their characteristics, and status.
Answer option A is incorrect. The communications management plan defines who needs what information, when the information is needed, and the modality the information is to be communicated in.
Answer option D is incorrect. The risk management plan defines how risk will be managed within the project.
Which of the following is NOT a valid maturity level of the Software Capability Maturity Model (CMM)?
A . Managed level
B . Defined level
C . Fundamental level
D . Repeatable level
Correct answer: C
Fundamental level is not a valid maturity level in the Software Capability Maturity Model (CMM).
The maturity levels of CMM are as follows:
1.Initiating level: At this level, processes are performed on an ad hoc basis. 2.Repeatable level: At this level, project management practices are institutionalized.
Defined level: At this level, technical practices are integrated with management practices institutionalized.
Managed level: At this level, product and process are quantitatively controlled.
Optimizing level: At this level, process improvement is institutionalized.